Preventive Maintenance Scheduling with Age Replacement Method at CNG Station

Cicilia Bangun (1) , Abdul Jalil (1) , Derajat Amperajaya (1) , Roesfiansjah Rasjidin (1)
(1) University of Esa Unggul, Indonesia

Abstract

CNG Mother Station focused to distribute Compressed Natural Gas for various industries. In the period from December 2020 to November 2021, there were 40 breakdowns in the distribution process machine causing delays in distribution of CNG. Company has to pay attention to the maintenance scheduling for vulnerabl components. This study aims to determine Preventive Maintenance scheduling and calculating maintenance costs using Age Replacement method for the critical components. The results showed that the critical components are Air Supply’s Hose (ASH) and Double Nipple Stage 4 (DNS-4). The proposed optimal replacement time interval for the ASH is 20 days where 19 component replacements are scheduled in 1 year with a cost reduction up to 4.8% compared to existing. The optimal replacement time interval for DNS-4 components is 24 days, which is scheduled for 16 component replacements in 1 year with cost reduction up to 29.1% compared to existing.

Full text article

Generated from XML file

References

Sukendar, I., Syakhroni, A., Prawira, M.R. (2020). Analysis of the age replacement method to reduce tool downtime. International Journal of Education, Science, Technology and Engineering, 3(1), 1-12. DOI: 10.36079/lamintang.ijeste-0301.41.

Fikri, N.A., Widjajati, E.P. (2020). Penentuan Interval Perawatan Mesin Air Separation Plant Secara Preventive Downtime Maintenance Dengan Menggunakan Metode Age Replacement Pada PT. XYZ. Jurnal Manajemen Industri & Teknologi, 1(3), 153-164, DOI: https://doi.org/10.33005/juminten.v1i3.114.

Andriani, Romli, I. (2020). Preventive Maintenance Pada Mesin Die Casting Dengan Age Replacement Model Untuk Peningkatan Reliabilitas Mesin. Operation Excellence, 12(1), 1-12, DOI: https://dx.doi.org/10.22441/oe.2020.v12.i1.001.

Misra, K.B. 2008. Handbook of Performability Engineering, Springer, Verlag London Ltd.

Rasjidin, R., Wahyuningrum, I. (2005). Analisis Preventive Maintenance Jig Welding Pada Proses Perakitan Support Assy Clutch Pedal Untuk Mobil Toyota Kijang Innova Di PT. Nusa Toyotetsu Corp. Jurnal Inovisi TM, 4(2), 91-98.

Stenstro¨m, C., Norrbin, P., Parida, A., Kumar, U. (2016). Preventive and Corrective Maintenance – Cost Comparison and Cost –Benefit Analysis, Structure and Infrastructure Engineering, 12(5), 603-617, https://doi.org/10.1080/15732479.2015.1032983.

Barraza-Barraza, D., Limon-Robles, J., Beruvides, M.G. (2014). Maintenance-Related Costs in Maintenance Management, ASEM 2014 International Annual Conference, Virginia Beach, DOI: 10.13140/2.1.1894.6568.

Praharsi, Y., Sriwana, I.K., & Sari, D. M. (2015). Perancangan Penjadwalan Preventive Maintenance Pada PT. Artha Prima Sukses Makmur. Jurnal Ilmiah Teknik Industri, 14(1), 59-65.

Kurniawan, F. (2013). Manajemen Perawatan Industri: Teknik dan Aplikasi Implementasi Total Productive Maintenance (TPM), Preventive Maintenance dan Reliability Centered Maintenance (RCM). Yogyakarta, Graha Ilmu.

Jardine, Andrew, K.S. (2006). Maintenance, Replacement, and Reliability: Theory and Application, Second Edition (Mechanical Engineering). London, Taylor & Francis Group.

Authors

Cicilia Bangun
[email protected] (Primary Contact)
Abdul Jalil
Derajat Amperajaya
Roesfiansjah Rasjidin
Bangun, C., Jalil, A., Amperajaya, D. ., & Rasjidin, R. . (2022). Preventive Maintenance Scheduling with Age Replacement Method at CNG Station . Aptisi Transactions on Technopreneurship (ATT), 4(2), 153–163. https://doi.org/10.34306/att.v4i2.260

Article Details